MRP logic and BOM (Without Considering Lead Time)

1. Product M consists of two units of N and three of P. N is comprised of two units of R and four units of S. R is made of one unit of S and three units of T. P consists of two units of T and four units of U.

a. Show the bill of materials (draw product structure tree).

b. If 100 M are required, how many units of each component are needed?